How to Know if a Building Has Flammable Cladding?

How to Know if a Building Has Flammable Cladding?

Learn how to know if a building has flammable cladding through test reports, core samples, and visual checks, plus what makes a cladding system genuinely safe.

Louis Major 8 min read

    You can tell if a building has flammable cladding by checking the product’s fire test certification, pulling a core sample for lab testing, and confirming the system passed a full-scale fire test such as BS 8414. None of this requires an engineering degree. A building certifier, fire engineer, or even a project manager can get clear answers within a few weeks. The harder part is knowing what to ask for and what a passing result actually looks like on paper.

    Why Does This Question Matter So Much Right Now?

    Because thousands of buildings across Australia still carry cladding that was never meant to go above a few storeys. After the Grenfell Tower fire in London in 2017, investigators found aluminium composite panels with a polyethylene core covering the outside of the tower. The fire travelled up the building’s face in under fifteen minutes. The panels had been tested as flat sheets in a lab, never as a full system fixed to a real wall. That gap between lab conditions and real installation became the centre of building regulations in the United Kingdom reform, and Australian states ran their own audits soon after. They found similar panels on apartment towers in Sydney, Melbourne, and Docklands.

    One of my clients managed a six storey apartment block in Melbourne. He called us in 2019 after a state cladding audit flagged his building. He had no idea what was behind his own walls, and he had owned the building for eight years. That gap in knowledge is more common than most owners want to admit.

    What Documents Should You Ask For First?

    Start with three things: the fire test report, the Certificate of Conformity, and the supply contract naming the exact product installed. Without these, nobody can confirm what is actually on the wall.

    • A full-scale test report under BS 8414 or the Australian equivalent, AS 5113
    • A cone calorimeter result for the specific product, not a similar one from the same supplier
    • Compliance paperwork matching the building’s classification and height under the National Construction Code

    A cone calorimeter is a small bench-top device that measures how much heat, smoke, and flame a sample gives off when exposed to a constant heat source. It is a quick way to screen a material before anyone commits to the cost of a full-scale system test. If a supplier cannot produce this result for the exact product on your building, that is your first red flag.

    Combustibility and flammability are not the same thing, and the difference matters when you are reading a report. A combustible material can burn and adds fuel to a fire. A non-combustible material does not add fuel, even under direct flame. Under AS 1530.1, a product is tested and rated against this exact line. Cladding systems installed on buildings above certain heights in Australia must now meet non-combustible requirements for the external wall system, following the same reasoning that drove reform overseas.

    How Do You Physically Check the Cladding Itself?

    Paperwork can go missing or get mismatched to the wrong product. A physical check backs it up.

    Start with a visual inspection. Knock on a panel near an edge or a damaged corner. Thin aluminium skin sounds and feels like a drink can. Look at any exposed edge or gap where a panel has come loose. If you can see a core material, note its colour and texture before anyone patches it up.

    A core sample is the next step and the most reliable one. A small section of the panel is drilled or cut out and sent to an accredited lab. The lab runs a cone calorimeter test on the actual material, not a sample from a catalogue. This tells you precisely what is behind the finish, rather than relying on what the original paperwork claims was specified decades ago.

    When we did a site visit for a commercial building in Brisbane, our installer noticed the cladding sheets were held on with adhesive rather than mechanical fixings, and a strip of foam was visible at one damaged corner. That single detail told us more than any file of paperwork sitting in the owner’s office. We recommended a core sample before anyone signed off on a remediation plan, and the lab confirmed polyurethane foam insulation behind the panel face.

    Polyurethane foam shows up often in older cladding and insulation systems because it is cheap and performs well for thermal insulation. The problem is what happens when it burns. It melts, drips, and releases flame quickly, which speeds up vertical fire spread across a building face. If you spot foam behind a damaged panel, or your paperwork lists a foam core insulation board, treat that as a reason to get a proper test done, not a reason to assume it is fine because it has been there for years without incident.

    What Makes a Material Actually Pass or Fail a Fire Test?

    BS 8414 builds a full-scale wall and insulation system, lights a fire at the base, and measures how far and how fast flame climbs the face over a set time, usually between fifteen and sixty minutes depending on the test variant. A product passes when flame spread stays under the defined limit and the system does not shed flaming debris onto people below. Flame spread is the measurement that decides everything here. A product can look solid and feel heavy in your hand and still fail badly once it is set alight as part of a full wall assembly, because the behaviour of the whole system matters more than any single layer.

    This is also where composite material gets confused with itself. Not every composite material behaves the same way under fire. Aluminium composite panels with a polyethylene core failed BS 8414 testing repeatedly, which is why they were pulled from use on high-rise buildings across multiple countries. Composite timber cladding uses a completely different core structure and manufacturing process, and products in that category are tested separately under AS 5113 against the fire provisions relevant to the applications they are rated for. Lumping every composite product into one basket is one of the most common mistakes I see building owners make when they are trying to self-assess risk.

    Who Actually Runs This Testing and How Long Does It Take?

    A NATA-accredited lab runs the core sample and cone calorimeter testing. A fire engineer then reviews the result against the building’s classification under the NCC and advises whether remediation is required. For most buildings, a core sample result comes back in two to four weeks. A full BS 8414 test is a different scale of project entirely. It usually sits with the manufacturer rather than an individual building owner, takes months to schedule and run, and costs tens of thousands of dollars because an entire wall section has to be built and burned.

    This is why most owners start with a core sample and documentation review rather than commissioning a brand-new full-scale test. The core sample tells you what is actually there. The documentation tells you what was supposed to be there and whether it was already tested as part of an approved system.

    What Can You Spot From the Ground Without Climbing a Ladder?

    Some warning signs don’t need specialist equipment:

    • Panels that look like thin, flat aluminium sheets rather than a textured or profiled board
    • Bulging, bowing, or discoloured panels near balconies, meter boxes, or anywhere heat has touched the surface before
    • Uneven joints or visible gaps where water has clearly been getting behind the face for years
    • Your building appearing on a state cladding register, such as the list maintained in Victoria or the Project Remediate scheme in New South Wales

    None of these confirm a failure on their own. They tell you where to focus the core sample and documentation request, which is far more useful than guessing.

    Why Choose a Cladding That Removes This Question Entirely?

    The owners I speak with are tired of chasing paperwork, chasing contractors, and still not having a straight answer about what’s on their building. That is the real cost of combustible cladding systems. It isn’t only the fire risk, it is the years of uncertainty afterward.

    Futurewood Cladding is manufactured and supplied as a composite timber product tested against the relevant Australian standards for the applications it is rated for, with documentation available upfront rather than something you have to track down after the fact. Once it’s properly installed, it does not need painting, sealing, or the ongoing upkeep that timber or ACP systems demand. Owners get a wall that looks right for decades without the maintenance cycle other materials lock them into, and without the dread of a future audit turning up a surprise behind the finish.

    What Should You Do Next?

    Request the fire test report and Certificate of Conformity for your building’s exact cladding product this week. If the supplier cannot produce it, or the document doesn’t match what’s physically on your wall, arrange a core sample and send it to a NATA-accredited lab for cone calorimeter testing before you spend money on anything else. That single step tells you more than any visual inspection ever will.

    If you’re concerned about Fire safety in your building, start by requesting the fire risk assessment from your building owner or managing agent, as this document should identify the type of cladding installed and any associated hazards. You can also check official construction records or planning documents held by the local council, which often specify the materials used on the exterior walls. Visually inspecting the building may offer clues, but cladding composition cannot be confirmed by sight alone, so written confirmation from a qualified surveyor or fire safety professional is the most reliable way to determine whether flammable materials are present.

    Louis Major

    About the author

    Louis Major

    Business Development Manager

    Louis is passionate about composite timber and low maintenance building materials, customer service and making sure that our customers are given all the information that they need to make an informed decision about their project.

    Married with a 2 year old son that loves to help in the business by stacking up composite timber colour samples.

    FuturewoodNovember 5, 2026